 P Eng Suraj Singh Faridabad NCR Delhi |
| Blog | Posted By: suraj on:5/1/2012 11:08:48 AM |
Novation Agreement
(Draft)
Project: 225
MW Gas based Power Project at ……………………, India - Phase-I
Part A
Brief
explanation of contractual terms ‘Novation’ & history for executing ‘Novation’
agreement:
Article meaning of ‘Novation’
Novation is a substitution of a new for an old debt. The old debt is
extinguished by new one contracted in its stead; a novation may be made in
three different ways which form three distinct kinds of novations.
NOVATION AGREEMENT-Contractual meaning
1.
A
legal instrument executed by (a) the contractor (transferor), (b) the successor
in interest (transferee), and (c) the by which, among other things, transferor
guarantees performance of contract, transferee assumes all obligations under
contract, and purchaser recognizes the transfer of contract and related assets.
2.
Substitution of a new contract for an old one. New agreement
extinguishes rights and obligations that were in effect under old agreement.
3.
A novation ordinarily
arises when a new individual assumes an obligation to pay, that was incurred by
original party to the contract. It is distinguishable from situation that
occurs when another individual makes a guarantee that a debtor will pay what he
or she owes to a creditor. In case of a novation, original debtor is totally
released from obligation, which is transferred to someone else. Nature of
transaction is dependent upon agreement between parties.
4.
A novation also,
takes place when original parties continue their obligation to one another, but
a new agreement is substituted for old one.
Statutory
provision-Indian Contract Act-
Section 62, Provides
Effect
of novation, rescission, and
alteration of contract.
If
parties to a contract agree to substitute a new contract for it, or to rescind
or alter it, original contract need not be performed.
Part B
Contractual History leading To This Novation of Existing Original
Subcontract Agreement.
1. M/s. ………………..2nd party on main contract, a contractor
to M/S…………………….. 1st
party on main contract entrusted certain supply & erection contract in
capacity of subcontract to M/S …………………….2nd
party on subcontract, designated on lower tier profile subcontracting status.
2. M/S ………………….EPC contracting company, 1st party on main
contract, allowed tacitly this lower tier subcontractor, ………………..2nd party on subcontract on
project based on tacit request for approval by M/s. ………………………………..2nd
party on main contract.
3. M/S ………………2nd
party on subcontract performed to its capacity & competency on project, a
considerable quantum of subcontract work, as included within referred
hereinafter/under, subcontract.
4. Due to reason beyond control of
EPC contractor M/S ………………….1st
party on main contract, contract that existed between M/S ………………..1st party on main contract, &
contractor M/s. …………………2nd party on main contract, has been
terminated effective dated 23 March, 2012 by serving on termination notice
under mandate of contract articles enjoyed by 1st party M/S ……………..EPC contracting company, 1st
party on main contract within that contract.
5. By virtue of this termination of contract by M/S ……………….EPC contracting company, 1st
party on main contract, M/s. ………………..2nd party on main contract has
lost all its contractual rights to participate on contract & project
actively.
6. A considerable amount has also, not been paid by
contractor M/s. ………………..2nd party on main contract to its
subcontractor M/S ………………………2nd
party on subcontract. In consequence of which, subcontractor M/S 2nd party on subcontract registered
an official complaint with ……………………..EPC contractor M/S contracting
company, 1st party on main contract, dated 20 March, 2012 regarding
an outstanding subcontract payment due to an extent of 102.53 lacs that M/s. …………………………..2nd
party on main contract should have paid to subcontractor but, that did not
realize.
7. M/S ……………… …………….contracting company, 1st party on main
contract, currently, concerned about unforeseen & uncertain future of this
project, resolved jointly & severely, to prosecute relevant critical
element of erection & installation remaining to go activities on scope of
contract, by engaging optionally, an alternative arrangement of sourcing, appointing
either to already mobilized & working entity or to procure a new one on
risk & cost of Terminated contractor.
8. Keeping abreast project interest that can contribute
saving & minimizing project lost duration, facilitating an earliest possible
delivery of product, M/S …………………………EPC
contracting company, 1st party on main contract elected to negotiate
with already mobilized entity namely M/S ………………….2nd party on subcontract relating to continuation of their
scope of works from progress achievement percentage mark that they reached on
day of Contract termination onwards for whole remaining scope of subcontract on/under
Terminated contract provided, M/S …………………………..EPC contracting company, 1st
party on main contract shall protect their subcontract’s due interests in all
respects contractually, sub-contractually, operationally, legally & by law
of Novation under provision of Indian Contract Act as well as, relevant common
law provisions, whatever could be admissible according to law within India. Consequently,
M/S …………. ………..EPC contracting
company, 1st party on main contract & M/S …………………….2nd party on subcontract jointly attempted
successfully for proposition of Novation of subcontract under purview of
Terminated contract. Due to foregoing causes, both parties have decided to
enter into novation of enforce subcontract, which details for incorporation on
that document composition, design/drawn body of Novation of Contract, is given
below for purpose of contract execution under purview of India Contracts Act.
Part C
Operations of Contractual Clauses & relevant
provisions included within contract between M/S ……………..EPC contracting company, 1st party on main
contract & M/s. ………..2nd party
on main contract:
1. Since, M/s. ………………….2nd party on main contract
contractor has been terminated effective dated 23 March, 2012, project
performance cannot be allowed to be effected adversely due to fact that
already, more than 39 weeks have been lost consequently, delaying project final
delivery to client.
2. General purchase conditions clause 21.0.0 Assignment
& subletting provides, as given below:
·
Clause 21.1.0 Except for raw materials work
of ancilliaries of supplier or part of this order for which makers are named in
approved vendor list, supplier shall not assign order or any part thereof, or
sublet order or any part thereof, without prior written consent of purchaser.
·
Clause 21.2.0 Supplier to furnish purchaser
two unpriced copies of all suborders issued for direct deliveries subvendor items
as agreed upon, within seven days of placement of such orders.
·
Clause 42.0.0 Supplier’s default & under
it Clause 42.5.0
·
If purchaser shall think fit, it shall be lawful
for him without prejudice to any other right he may have under order to
take supplies wholly or in any part out of supplier’s hands & reorder
with any person or persons to complete contract/order or any part thereof.
·
Inference & construction from foregoing
clauses provisions permit without being limited by any contractual
qualification or reservation, M/S ……………………….EPC
contracting company, 1st party on main contract, to elect & to
resolve Termination risk sever impact, which impedes running/earned progress negatively
on foregoing project by appointing, either a new party or an existing agency on
project, so as project progress time loss adverse effect is minimized & if
not, at least, optimized within application of projects control methodology.
Novation Agreement/Contract
Objective of main contract is to
deliver EPC demands/requirements for Ultimate Purchaser
Company/Client/Owner/Ultimate Purchaser:
M/S ……………………….EPC contracting
company, 1st party on main contract
Contract Form:
Part D
Definition on this Novated Contract
parties:
1. First
Party: M/S ………………..EPC contracting company, 1st party on main
contract Called EPC Contractor/Employer,
who has undertaken to deliver EPC services to M/S ………………………….client as indicated above.
2. Second
Party: ……………………………..previous 2nd
party on terminated contractor’s subcontract, who had undertaken a service
subcontract/purchase order for supply & erection services of plant facility
installation as defined in details vide their old contract agreement reference
from …………………………………..2nd party on main contract, 1st
party on subcontract Email- ………………. address references Order number …………………………………………..
issued via GPI reference ………………………………..with original first party, as named
hereinafter,
3.
Original First party: M/s. …………………………………2nd party on
main EPC contract, now stands terminated of its Contract, on this day of this
Novation agreement is entered into/executed, between M/S ………………………..2nd party on novated contract, former 2nd party on
subcontract & M/S ………………………………..EPC
Contractor/Employer.
4.
Original Second party: M/S ………………………….2nd party on novated
contract, former 2nd party on subcontract, address…………………………E mail
………………………………. hereinafter, called contractor for exactly true scope that it had
to prosecute within its subcontract, as referred in foregoing with M/S.
………………………2nd party on main EPC contract.
5.
Both new contract parties by virtue of this Novation,
agree as follows, respecting title project:
·
First party: M/S …………………………..EPC contracting company, 1st party
on main contract. Hereinafter called Employer/Purchaser.
Reference included above
·
Second party: M/S …………………………..2nd party on novated
contract, former 2nd party on subcontract. Hereinafter
called Contactor. Reference included above
·
Terminated
party: M/s. ……………………………..2nd
party on main contract hereinafter called Terminated party.
Reference included above
Other Provisions:
1.
Date of Novation: This Novated contract comes
into effect immediately, appointed date of enforcement being 24 March 2012.
2.
Performance Security/Guarantee:……………………
3.
Date of Subcontract & this Novated
Contract Mechanical Completion:…………………
4.
Date of Contract Final Completion:………………….
5.
Revised Liquidated damages: ……………………..
6.
Defects Liability period: …..from final
handing over/completion
7.
Subcontract Amount:……………………..
8.
Percentage of subcontract works completed
cost wise: 89%
9.
Amount received by subcontractor:……………………..
10.
Outstanding Amount On subcontract:…………………………..
11.
Percentage of subcontract works yet to be
completed:11% of subcontract purchase order
12.
Amounts due to remedial or corrective works,
not due to fault of contractor on subcontract, if applicable:………………………………
Part E
Terms &
conditions-General/Contractual:
1. Novation Contract Documents: precedence
-This contract form, Subcontract
enforce under Terminated Contract, all financial/commercial documents
constituted under subcontract & forming it, MOM dated 5 Feb 2012 under
subcontract ambit, all technical & engineering drawings & sketches, all
relevant specifications, all communications with Novated contractor post
Termination of Contract, Contract provisions under scope of contract reference
(terminated contract) 1st
party/employer/001/MECH/HRSG/WO/003/2010 Dated: 25.05.2010, awarded under
provision 18.0, Award of contract covered within chapter ‘Instruction to
bidder’ to an extent of scope items, activities & works applicable under
subcontract & Novated contract, shall together constitute contract
documents which all, shall be construed with mutual recognitions with each
other & collectively to define, on or for every consideration or resolution
of disputes.
2. Sequence
to contract documents construction for interpretation/inference.
Precedence to documents shall be followed as
indicated below for purpose of interpretation or construction of documents
contractual relations definitions.
This
contract/Statutory inspection requirements/Terminated Contract/Subcontract
& MOM or other records within its purview or ambit/Design Drawings/Working
drawings/Shop/Installation drawings/Specifications/schedules/industrial
conventions & general practices etc.
Agreement in principle By
Employer:
1.
Employer agrees to pay all outstanding dues/monies
to Contractor that he had to receive from subcontract prosecuted works in line
to terms & conditions provided in relevant paragraphs below under
‘Payments’. This amount shall be released in proportion in due course in
installments & as referred under Payment clause below.
2.
Employer agrees to pay all monies, which
shall become due to be paid to contractor in future for all works carried out
or prosecuted/performed by contractor satisfactorily until, whole project
within its scope is delivered.
3.
Employer agrees to commit, honour, regard,
observe & comply with, all provisions that were included within
subcontract, saving exceptions specifically included or revised herein to be no
more applicable on subcontract, which this contractor had agreed with
Terminated contractor.
4.
Employer agrees not to impose any Liquidated
Damages clauses that were applicable on Terminated contract on to this
contractor until, day of this Novation agreement is executed.
5.
Employer agrees to do, act, carryout, manage,
provide all requirements whatsoever, that constituted as similar activities on
Terminated party’s responsibilities.
Agreement in principle By
Contractor:
1.
Contractor agrees to carry out all remaining
works or activities, not performed under original subcontract that is an
integrated part of this contract henceforth, for all contractual & legal purposes.
2.
Contractor also, agrees to obtain approvals,
process procurement, deliver to site, install or erect, & effect all
following in sequence activities until, carried out works are delivered
satisfactorily in compliance with provisions of relevant terms & conditions
on terminated contract, a copy of which shall be provided to contractor.
3.
Contractor also, agrees to deliver
installations on date of completion appointed herein without causing any
further delay under any circumstances that are within contractor’s controls.
4.
Contractor also, agrees to allow a new LD specified
above per day or part of a day & after accumulation, deductable not more
than an amount specified in foregoing LD provision.
5.
Contractor agrees to own full contract
responsibility, accountability, liabilities & all other deeds & acts,
that shall be required by contractor to carry out on remaining works on
contract as well as, remedial works, if so required from previous subcontract.
6.
Contractor agrees to comply with all
relevant, pertinent provisions included within Terminated contract, those shall
be applicable for prosecution of various works & activities with an
understanding that all such terms & conditions would remain in force till
completion of all works within scope of this contract as well as, in
subcontract.
7.
Contractor agrees to own responsibilities &
obligations in a similar manner or fashion as were agreed in full implications
by terminated contractor, to an extent full scope of this contract &
subcontract is related.
8.
Contractor agrees to comply with all
requirements respecting standard engineering construction industrial practices
for disciplines such as, quality controls, quality requirements/assurances,
health, safety & environment etc. Project safety is governed under using
required safety equipment on all operations all times. Quality controls &
quality assurance/requirements are governed by standard testing procedures for
various activities & compliance to strictly adhering to quality procedures
& documentations to an extent required within scope of this contract.
Part F
Payments:
1.
An amount rupees 20 lacs (twenty lacs only) shall
be paid to contractor immediately, for meeting very urgent requirements to keep
activities moving. This allowance shall be considered as an advance payment against
provision of surety (to be decided).
2.
Recoveries of this advanced sum, has to be
adjusted on running /interim payments that shall be approved for carrying out
remaining scope of works.
3.
Progressive payments shall be made in proportion
to works carried out prior to novation & only, when works are accepted
after quality & quantity measurements.
4.
Contractor shall provide to employer or
purchaser all evidences of whatever payments were received by him from
Terminated contractor. All subcontract priced documents shall constitute part
of this contract.
5.
Contractor shall also, provide an attested
copy of original work order & payment certificates received from Terminated
subcontractor.
6.
Contractor shall undertake to record with employer/purchaser,
any further payment received post Termination of contract.
Part G
Special Conditions:
1.
Suspension
of works restriction: Avoidance of suspension of works- Both
parties undertake to avoid to a maximum extent possible, any move to suspend
any part of scope of remaining works, so that appointed target date for
completion is achieved successfully. Suspension of works conditions shall be
applied only when, circumstances occur very remotely beyond controls of either
party namely force majeur of serious nature like natural calamity.
2.
Application
of efficiency on works-All works covered in this contract purview
shall be carried out promptly without involving any remaining time wastage
even, utilizing holidays for work to maximum extent without concerning about
overtimes payments to involved personnel. Piece work payment rate shall be
preferred to be applied on performance of this scope of contract.
3.
Encountering
problems-In case of certain problems are encountered
unforeseen relating to causing delay on works & contractor is unable to
resolve it, contractor shall immediately, inform employer to extend assistance
for resolution for an earliest achievement of installations.
4.
Transfer
of responsibilities & liabilities-By virtue
of this novation agreement, all responsibilities that were shared by Terminated
contractor till day of Termination, now, henceforth, shall be shared in full by
employer to an extent project management / administration is concerned.
Contractor shall report to employer for any issues involved whether,
contractual, statutory, cost wise, commercial, managerial or others.
5.
Relations with Terminated contractor-Contractor
shall have no more functional or contractual relations with Terminated
contractor. Contractor shall provide all available documents of any sort whatsoever,
relating to subcontract under Terminated contract, to process all those documents
as a part of this contract for all contractual & legal purposes.
6.
Disputes with Terminated contractor- Novated
contractor shall not deal with any dispute that exists due to any cause
pertaining to period prior to this novation agreement. It shall be
responsibility of employer/purchaser to deal contractually, legally or
otherwise, with Terminated contractor. Novated contractor is required to
complete its scope promptly with defined time schedule quantitatively &
qualitatively.
Part H
Communications:
Between
contract parties
1. Contractual-Preferable
medium E mails, 2nd is by faxes followed original by couriers,
contract meetings, progress review meetings, work done valuations etc.
2. Technical-
technical queries, clarifications, method statements, procedures, approvals
etc.
Part I
1.
Insurances-
All insurances by third party for all personnel shall
operate according to law of India applicable in project location region.
2.
Safety-
safety shall be conducted according to project safety plans & relevant
industrial safety procedures adhered with.
3. Contract Jurisdiction for Adjudication of
disputes: ?